Skip to...
The facts
Project overview
Key Achievements
Industry Sectors
The Facts
420km GLNG DN1050
Service of Main Line Valve Stations
Pipeline Defect Repair
Project Overview

Nacap were engaged by GLNG Operations to provide all services in connection with the pipeline repair and rehabilitation on the 420km GLNG DN1050 Gas Transmission Pipeline (GTP), stretching from Fairview near Injune to Curtis Island near Gladstone. The object of repair is to ensure that repaired pipe is fit for service over remaining pipeline life, having sufficient structural integrity to withstand all identifiable forces to which it may be subjected during operations, including the Maximum Allowable Operating Pressure and cyclic pressure fluctuation, with an acceptable safety margin.

read more
Key Achievements

Tasks executed successfully and ongoing maintenance contract in place.